Einsatzpotenziale von Large Language Models in der Produktionsplanung
: eine Fallstudie am Beispiel der kurzfristigen Neuverplanung in der Kleinserien- und Prototypenfertigung

  • Johannes Reithofer

    Student thesis: Master's Thesis

    Abstract

    Short-term disruptions, material shortages, changes in priorities, and fluctuations in capacity make rescheduling in small-batch and prototype environments with a wide variety of product variants a challenging decision-making task.

    The goal of this thesis is to investigate the potential of Large Language Models (LLMs) for short-term production rescheduling and to compare their results with those of human production planners. Based on the theoretical foundations of production planning and LLM evaluation, an application-specific selection framework and an evaluation model are developed, incorporating the dimensions of feasibility, schedule quality, rescheduling quality, bottleneck management, and explainability.

    The case study at Peak Technology includes eight identical rescheduling scenarios. Four production planners process these in WayRTS; the LLM application systems receive a data set equivalent in content via structured Excel exports, master data, and an explicit set of planning rules. A technical pilot involves ChatGPT, Grok, and Microsoft Copilot. Since Copilot was unable to generate editable XLSX files in the tested configuration, the main qualitative comparison of plans includes 32 human-generated and 16 LLM-based plan revisions from ChatGPT and Grok, for a total of 48 results. Of these, 36 pass the feasibility check. The human group produced 27 out of 32 feasible plans (84.4%). ChatGPT generated seven out of eight feasible plans (87.5%) and Grok two out of eight (25.0%). ChatGPT demonstrated competitive results, particularly in limiting plan changes, managing bottlenecks, and providing standardized justifications. Humans, on the other hand, demonstrate higher collective feasibility and unanimously solve the complex combined scenario S10 as feasible, while both LLM systems fail. Early rough deadlines repeatedly prove unusable when capacity, lead time, or process sequence rules are violated.

    Overall, no planning group can be said to have a general advantage. The results support an assistive approach in which an LLM generates a specific plan proposal and its rationale, a formal validator checks for hard constraints, and operational approval remains with the production planners.
    Date of Award2026